The Challenge
Following an acquisition, the acquiring company brought in New Oaks with six weeks to eliminate a six-month production backlog, transfer all equipment and inventory, and return the leased facility in pristine condition.
The Stakes
Missing the deadline would trigger significant financial penalties. Production recovery, inventory management, asset transfers, facility decommissioning, and contractual closeout all had to be completed within 42 days.
The Result
✦ Deadline Met: Completed the entire project within six weeks.
✦ Production Cleared: Eliminated the complete six-month backlog.
✦ Financial Penalties Avoided: Returned the facility on time and met all lease conditions.
✦ Contractual Obligations Fulfilled: Transition completed without disruption to buyer operations
✦ Assets Successfully Consolidated: Transferred $20M in inventory and equipment to the buyer’s facilities.
The Solution
New Oaks planned and managed continuous operations supported by comprehensive, on site project management.
24/7 Production
Implemented around-the-clock shifts to eliminate the production backlog while maintaining quality control and recording zero safety incidents.
On-Site Management
Placed experienced New Oaks personnel on every shift to resolve problems and make decisions in real time.
Logistics & Asset Transfer
Completed the physical inventory, supported local inventory valuation, coordinated the transfer of sellable inventory, executed facility decommissioning, and managed the destruction of obsolete and scrap inventory with documented chain-of-custody and customer verification records.
Facility Closure
Managed final cleaning, verified return conditions, and coordinated all facility handover documentation.